Compass Mining Facility Update: October 27

Compass Mining Facility Update: October 27

Compass Mining is pleased to provide the following facility updates for October 27, 2022.

Compass Mining Facility Update: October 27

Please note the structure used below for all Compass products:

  • Facility updates: updates on any facility changes, including moving miners between locations, downtime, or general information about one of Compass’s partner facilities.
  • Deployment updates: updates on current deployments from manufacturers to Compass hosting locations.
  • Bundle updates: information on individual bundle deployments or re-locations can be found here.

Helpful Links:

  • Your Compass Dashboard for your order information.
  • Compass Status page for real-time updates on facility status.
  • Naming conventions for each facility here.

Facility Updates

Compass Mining Facility Update: October 27
Texas 4

Texas 4: Compass Mining is proud to announce our newest partner facility, Texas 4, with Aspen Creek Digital Corporation (ACDC).

Certain S19 XP units are eligible to go live at Texas 4 within the next two weeks and have been contacted via email for selection.

Read: Compass Mining Signs 27 MW Hosting Agreement With Aspen Creek Digital Corporation (ACDC)

Texas 3: MINI Bundle, Lonestar Bundle 1 & 2, VIP Bundle, R-NA bundle units and S19j Pro singles are all slated to come online at Texas 3.

2,000 units are now deployed. We remain on standby for a further 6,000 unit deployment, which will follow chronologically with re-deployments and bundle dates. We continue to wait for approval from ERCOT following unexpected maintenance in late September on the site’s substation.

Compass Mining has sent out details for a client ‘Q&A’ session scheduled for Thursday, November 3 at 10:30 am EST. The call will be viewable on our YouTube account and clients will be emailed the link prior to the event.

Georgia 2 &3: 72% of units are now back online. We expect the final units to be deployed by Friday, October 28.

New Mexico: We have decided to end our contracting agreement with New Mexico after receiving client feedback about the site’s performance.

All New Mexico miners are currently undergoing inspection at the facility for the expected site closure at the end of November. Units have begun deracking and are moving to Texas 4 after inspection at our Denver, Colorado logistics and repair hub.

Please note that a small subset of units needing repairs were routed to Indiana 2 for redeployment in September. Those units are online as of Thursday, October 13.

Nebraska 1: One of the site’s transformers failed in early October. The on-site team continues to work on repairs. We have no time estimate for the site to be back online at this time, but continue to work with the team for an expedited fix.

Oklahoma 2: 72% of units are deployed at Texas 3. The final deployment of units are awaiting further energization at Texas 3.

Oklahoma 3: These units are now online at Indiana 2.

British Columbia 1: All units have been de-racked from British Columbia 1 and are now en route to Manitoba 8 for deployment by mid-November.

Deployment Updates

Texas 3: MINI Bundle, Lonestar Bundle 1 & 2, VIP Bundle, R-NA bundle units and S19j Pro singles are all slated to come online at Texas 3 after ERCOT further greenlights energization for the site’s remaining load.

Texas 4: Next Generation Bundle August Unit 1 and Unit 2, Next Generation Bundle September Unit 1, S19 XP August Single Units and S19 XP September Single Units are eligible to go live at Texas 4, after selection via email. Clients may elect to wait for Texas 3 to go live.