Compass Mining Facility Update: Oct 7

Compass Mining Facility Update: Oct 7

Our overall uptime across all sites last week reached 96.69%. For more information, please refer to the chart below:

Compass Mining Facility Update: Oct 7

Helpful links:

Facility Updates

Ontario 1:

This week, the facility maintained over 95% utilization with 100% uptime. The on-site team re-racked 19 miners, which returned after hashboard repairs. Additionally, the facility operator is improving the support ticketing system so we can better coordinate the efforts between the on-site and remote staff.

Ohio 2:

The on-site technicians have been focused on moving miners and reorganizing Container 9 to relocate miners to racks where they can hash without issues. Additionally, the team is working on a list of units that require fan repairs and diagnostics to improve the site's utilization.

Texas 1:

The facility has seen a slight improvement in utilization and uptime, with fewer curtailments this week. We are actively following up with the site's operator for feedback on the list of miners that need attention. We remain optimistic that the utilization at the site will improve as we see fewer curtailments.

Texas 5:

This week, the site experienced fewer curtailments, reflecting an improvement in facility uptime. The on-site team will continue to address repairs and diagnose issues with miners. 

Curtailments & Outages: 

The table below provides a summary of downtime across our facilities for the past week:

Facility

Number of Outages

Estd Start Time

Min Duration

Max Duration

Average

IN1

2

4 AM (EST)

2

4

4

IN2

2

4 AM (EST)

4

4

4

MB2

1

11 PM (EST)

1

1

1

MB4

1

3 AM (EST)

1

1

1

OH2

1

7 PM (EST)

1

1

1

TX1

2

9 PM (EST)

3

10

7

TX5

2

7 AM (EST)

1

3

2

MN1

2

6 AM (EST)

1

4

3

IA2

2

12 PM (EST)

3

4

4

IA3

2

12 PM (EST)

3

3

3

Deployment Updates

Please submit a ticket request if you have any questions or concerns.

We have turnkey miners ready for immediate deployment at some of our facilities. Here is a summary of the units we have available on the Compass website:

Facility

Miner Model

Units Available

Iowa 2

Antminer S21 XP 270TH

18

Iowa 3

Antminer S21 Pro 234TH

69

Minnesota 1

Antminer S21 195TH

115

Minnesota 1

Antminer S21 200TH

81

Ohio 2

Antminer S21 200TH

44

Ontario 

Antminer S21 188TH

120

Ontario

Antminer S21 200TH

116

Texas 1

Antminer S21 188TH

106

Texas 1

Antminer S21 195TH

95

Texas 1

Antminer S21 200TH

215

Relocation Updates

Texas 3 & Nebraska 1 Relocation

The new Nebraska 2 site is up and running, with 1600 miners hashing to customers already. Currently, only two out of three transformers are energized. Once we fix the third transformer, an additional 800 miners will be energized, bringing us to maximum capacity at NE2. The remaining TX3/NE1 relocation miners will be deployed at our other partner facilities in small batches.