Compass Mining Facility Update: Oct 21

Compass Mining Facility Update: Oct 21

Last week, our overall uptime was 98.86%, impacted by a decrease in curtailments and outages. For more details, please see the chart below:

Compass Mining Facility Update: Oct 21

Helpful links:

Facility Updates

Iowa 2 / 3:

The site has been undergoing maintenance to implement essential electrical upgrades. These enhancements aim to increase operational capacity and minimize the risk of future electrical issues. We will update you on our Status Page, as we progress.

Ontario 1:

The site has been experiencing cooler weather, which is positively affecting our operations. Consequently, the miner utilization rate is steadily rising, indicating enhanced efficiency. Our onsite team is continuing to troubleshoot miners and push utilization higher. 

Ohio 2:

The onsite team thoroughly cleaned the filters on two containers, ensuring optimal airflow and performance. Additionally, they have installed a carport over one of the containers. This new structure protects the hardware and prevents damage during heavy rains and storms. These measures are part of our ongoing commitment to improving the miner utilization at the facility.

Texas 1:

The site completed maintenance on the fan exhaust systems, which has led to a noticeable improvement in performance. The onsite team is actively diagnosing miners experiencing issues and working through the backlog. We are hoping for higher miner utilization rates over the coming few weeks. 

Texas 5:

The onsite team is replacing older PDU units with updated models to ensure improved performance and reliability. An electrician was on-site to facilitate this process and assist with the upgrades. In addition, our onsite team is systematically working through a comprehensive diagnostics checklist to identify and address any underlying issues. They aim to optimize the site's uptime and utilization, ensuring operations run smoothly and efficiently.  

Curtailments & Outages: 

The table below presents an overview of downtime across our facilities for the past week:

Facility

Number of Outages

Estd Start Time

Min Duration

Max Duration

Average

MB2

1

10 AM (EST)

14

14

14

TX1

3

6 AM (EST)

1

4

2

TX5

2

7 AM (EST)

1

2

2

MN1

2

3 AM (EST)

1

1

1

Deployment Updates

Please submit a ticket request if you have any questions or concerns.

We have turnkey miners ready for immediate deployment at some of our facilities. Here is a summary of the units we have available on the Compass website:

Facility

Miner Model

Units Available

Iowa 2

Antminer S21 XP 270TH

18

Iowa 3

Antminer S21 Pro 234TH

69

Minnesota 1

Antminer S21 195TH

115

Minnesota 1

Antminer S21 200TH

81

Ohio 2

Antminer S21 200TH

44

Ontario 

Antminer S21 188TH

120

Ontario

Antminer S21 200TH

116

Texas 1

Antminer S21 188TH

106

Texas 1

Antminer S21 195TH

95

Texas 1

Antminer S21 200TH

215

Relocation Updates

Texas 3 & Nebraska 1 Relocation

Only 1,700 TX3/NE1 relocation miners remain at the Denver Service Center, and they will be sent to our partner facilities in small batches. All of these miners are expected to be relocated within the next two weeks, marking the end of this relocation.