Compass Mining is pleased to provide the following facility updates for November 10, 2022.

Please note the structure used below for all Compass products:

  • Facility updates: updates on any facility changes, including moving miners between locations, downtime or general information about one of Compass’s partner facilities.
  • Deployment updates: updates on current deployments from manufacturers to Compass hosting locations.
  • Bundle updates: information on individual bundle deployments or relocations can be found here.

Helpful Links:

  • Your Compass Dashboard for your order information.
  • Compass Status page for real-time updates on facility status.
  • Naming conventions for each facility here.

Facility Updates

Texas 4: Compass Mining is proud to announce our newest partner facility, Texas 4, with Aspen Creek Digital Corporation (ACDC).

Certain orders are now online at Texas 4. Clients with the ability to go online at Texas 4 have received email communications. We ask clients to fill out the form as soon as possible if they wish to go online at Texas 4. Units are going online chronologically by order date.

Watch: Energy First With Renewable Miner ACDC

Read: Compass Mining Signs 27 MW Hosting Agreement With Aspen Creek Digital Corporation (ACDC)

Texas 3: MINI Bundle Unit 5 & 6, Lonestar Bundle 1 & 2, VIP Bundle, R-NA bundle units, M30S++ and S19j Pro singles are all slated to come online at Texas 3.

Two thousand units are now deployed. We remain on standby for further deployments based on order date. We continue to wait for approval from ERCOT following unexpected maintenance in late September on the site’s substation.

Compass Mining held a Q&A last week on the Texas 3 deployment schedule. You can find a blog summary here.

North Dakota: These units are now online at Texas 4.

Georgia 2 & 3: 95% of units are now back online. We are working with the on-site operator to get the remaining percentage of units back online.

New Mexico: We have decided to end our contracting agreement with New Mexico after receiving client feedback about the site’s performance.

All New Mexico units are now on-site at Texas 4, minus a subset of units identified for further repairs while at our Denver logistics and repair hub.

Nebraska 1: One of the site’s transformers failed in early October. The on-site team continues to work on repairs. We have no time estimate for the site to be back online at this time but continue to work with the team for an expedited fix.

Oklahoma 2: 72% of units are deployed at Texas 3. The final deployment of units is awaiting further energization at Texas 3.

Oklahoma 3: These units are now online at Indiana 2.

British Columbia 1: Units have arrived at Manitoba 8 and are being inspected before racking.

Deployment Updates

Texas 3: MINI Bundle, Lonestar Bundle 1 & 2, VIP Bundle, R-NA bundle units, S19j Pro singles, Single Order S19 XPs, Next Generation Bundle and certain M30S++ deployments are all slated to come online at Texas 3 after ERCOT further greenlights energization for the site’s remaining load.

Texas 4: S19 XP (Single unit orders and Next Generation Bundles) and Mini Bundle Unit 5 orders are available to go live at Texas 4. Please refer to our most recent email communication for more information.