Compass Mining Facility Update: June 17

Compass Mining Facility Update: June 17

Last week, our facilities had an overall uptime of 98.46%. The chart below provides details.

Compass Mining Facility Update: June 17

Helpful links:

Facility Updates

Indiana 1-2: The area around the facility is experiencing high temperatures, affecting the temperatures inside the facility. As a result, some miners are overheating, and the technicians are focused on mitigating the issues.

Ontario: The on-site technicians are performing maintenance on the exhaust fans to help manage overheating, as temperatures will likely continue to rise in the coming months.

Ohio 2: The deployment of new S21s and OH3 units at the facility is complete. Our on-site technicians are currently working on pending diagnostics and repairs. The technicians are also preparing for the next site expansion planned for this week.

Curtailments & Outages: Last week, the curtailments in Texas 1 and Texas 5 were quite frequent due to increased demand on the grid. This increased frequency of curtailment is said to continue throughout the summer. Manitoba 4 experienced downtime because of a network outage, while Ohio 2, Minnesota, and Manitoba 2 underwent scheduled maintenance. The table below summarizes the downtime across our facilities for the past week.

Compass Mining Facility Update: June 17

Deployment Updates

Please submit a ticket request if you have any questions or concerns.

Turnkey Miners

We have turnkey miners ready for immediate deployment at some of our facilities. Here is a summary of the units we have available on the Compass website:

Compass Mining Facility Update: June 17

Future Deployments

Antminer S21: We have acquired additional S21 turnkey units for upgrades. The units will soon come online in Texas 1.

Antminer S19K Pro: A shipment of Antminer S19k Pro miners has arrived at Texas 5, and we are waiting for them to be racked by the on-site technicians.

Relocation Updates

Texas 3 Relocation

The de-racking of Texas 3 units is progressing as planned. We have shipped approximately half of the Texas 3 units to the Denver Service Centre. Only a few miners are still in racks; the rest are being prepared for shipment.

Nevada and Indiana (partial relocation)

Relocation units are now online in Texas 1. Please contact us if you have not received any updates on your miner’s status.