Compass Mining is pleased to provide the following facility updates for June 12, 2023.
Summer mining is now here! Please note that all North America-based facilities are likely to experience heat related issues over the next few months as ambient temperatures surpass 80 degrees Fahrenheit. Follow the Compass Mining status page for site wide updates.
Please note the structure used below for all Compass products:
Helpful links:
Texas 5: Site technicians have ordered and received the new transformer, with an estimated timeline of re-energization early this week following the parts failure.
Florida 1: Certain units are being pulled from the site for transfer to Texas 5, following cleaning at our Denver Service Center. All clients affected were contacted via email.
Indiana 1 & 2: Site heat issues are being actively addressed through airflow work.
Bundles:
LoneStar 2: Unit 6 is 75% deployed. Deployments will continue as units are energized in Texas 3 and Texas 5.
Next Generation Bundle and/or S19 XP Single Orders: Remaining orders remain on standby. Unit allocations may go to alternative sites, depending on the best timeline for units to be energized.
Singles:
Antminer S19j Pro 100TH - Ohio 2 May 15th: Batch is fully deployed!
Antminer S19j Pro 100TH - Ohio 2 May 25th: Batch is fully deployed!
Antminer S19j Pro 100TH - Ohio 2 May 31st: Batch is fully deployed!
Antminer S19j Pro 100TH - Texas Sept. 2022: Batch is 91% Deployed. Deployments will continue as units are energized in Texas 3, with 90 left to deploy.
South Carolina 2 Relocation: 1,200 units are now on-site, minus a cohort of Whatsminers still being processed at our Denver Service Center. Units will be energized once the site’s breaker issue is resolved.
Whatsminers are expected to be processed this week for shipment to Texas 5 shortly.
Redeployed S19 XP (Former Texas 4 units): Units are now in cleaning, inspection and repair before redeployment. Please expect an invitation to a scheduled call with the Compass Mining operations team to discuss next steps.