Compass Mining Facility Update: June 10

Compass Mining Facility Update: June 10

Last week, our facilities had an overall uptime of 96.71%. The chart below provides details.

Compass Mining Facility Update: June 10

Helpful links:

Facility Updates

Indiana 1: Last week, the facility powered down for several hours as the local electricity provider repaired a broken pole. The onsite technicians promptly brought the miners back online once power was restored in the area.

Iowa 2: The facility experienced power outages on two occasions last week. Once the power was back on, the technician promptly restored all miners.

Ontario 1: The onsite team has successfully deployed all new S21 units that arrived at the facility. They have started addressing the backlog for diagnostics and repairs and continue to de-rack retired units to make space for incoming deployments and repaired miners.

Ohio 2: The onsite technicians were busy setting up the network in new containers for the site expansion. Several maintenance tasks were also completed at the facility last week to address the overheating issues.

Curtailments & Outages:

Last week, there was an increase in curtailments at Texas 1 and Texas 5 due to high demand in the area. Additionally, Indiana 1 and Manitoba 8 experienced downtime for maintenance. The table below summarizes the downtime across our facilities last week.

Compass Mining Facility Update: June 10

Deployment Updates

Please submit a ticket request if you have any questions or concerns.

Turnkey Miners

We have turnkey miners ready for immediate deployment at some of our facilities. Here is a summary of the units we have available on the Compass website:

Compass Mining Facility Update: June 10

Future Deployments

Antminer S21: We purchased additional S21 units to complete pending upgrades.

Antminer S19K Pro: We also ordered another batch of K Pro units to complete pending deployments.

Relocation Updates

Texas 3 and Nebraska Relocation

The onsite technicians are continuing to de-rack miners at the site. Last week, around 3,000 units were powered down to prepare them for shipment to DSC. When a miner goes offline, customers can expect that the unit is being prepared for relocation.

Nevada / Indiana (Partial Relocation)

The majority of the miners relocated from Indiana and Nevada have also been redeployed at Texas 1. Only a small number of miners are still pending redeployment. To increase space, we are de-racking retired and faulty units.

文 » A