Compass Mining Facility Update: Dec 30

Compass Mining Facility Update: Dec 30

Our overall uptime across all sites was 99.31% last week. For a detailed breakdown, please see the chart below:

Compass Mining Facility Update: Dec 30

Helpful links:

Facility Updates

Indiana 1 / 2:

The on-site team is working to enhance the site's infrastructure and improve the air filtering systems. This comprehensive work will take approximately three weeks to complete.

Manitoba 2-9: 

Following a significant snowfall that impacted our Manitoba sites, the on-site team resumed activities as soon as the weather improved. Their commitment and resilience ensured we could swiftly get back on track and continue operations despite the challenging weather conditions.

Ohio 2: 

The team has completed the deracks from last week and is now troubleshooting units. Additionally, the team has invested resources and time in the end-of-year audit, further slowing down actions. 

Ontario 1:

The on-site team has been busy installing new S21 units. The site also experienced several PDU failures that required immediate replacement. This week, the team will shift its focus to troubleshooting and diagnostics of units. 

Curtailments & Outages: 

The table below summarizes the downtime (including curtailment, power outages, and maintenance) at our facilities over the past week:

Facility

Number of Outages

Estd Start Time

Min Duration

Max Duration

Average

TX1

4

12 PM EST

2

6

5

MN1

1

9 PM EST

1

1

1

Deployment Updates

Please submit a ticket request if you have any questions or concerns.

We have turnkey miners ready for immediate deployment at some of our facilities. Here is a summary of the units we have available on the Compass website:

Facility

Miner Model

Units Available

Indiana 1

Antminer S21 Pro 234TH

100

Indiana 2

Antminer S21 200TH

25

Iowa 3

Antminer S21 188TH

89

Iowa 3

Antminer S21 195TH

49

Iowa 3

Antminer S21 200TH

95

Minnesota 1

Antminer S21 188TH

196

Minnesota 1

Antminer S21 195TH

218

Minnesota 1

Antminer S21 200TH

162

Nebraska 2

Antminer S21 188TH

149

Nebraska 2

Antminer S21 195TH

161

Nebraska 2

Antminer S21 200TH

67

Ohio 2

Antminer S21 200TH

35

Ontario 

Antminer S21 188TH

118

Ontario

Antminer S21 200TH

20

Relocation Updates

Texas 3 & Nebraska 1 Relocation

The remaining 800 units have been shipped to our new site in Texas. They are expected to be online this week. 

Texas 1 Relocation

Only 1655 units remain at the Texas 1 facility. They will be de-racked next week and shipped to our new site in Texas. 

Manitoba 2 & Manitoba 9 Relocation

The Manitoba 2/9 sites will begin relocating on January 5th. The process, including de-racking, transportation, cleaning, testing, and re-racking, is expected to take 6-9 weeks. Miners are expected to return online by March 2025.