Compass Mining Facility Update: April 17

Compass Mining is pleased to provide the following facility updates for April 17, 2023

Please note the structure used below for all Compass products:

  • Facility updates: updates on any facility changes, including moving miners between locations, downtime or general information about one of Compass’s partner facilities.
  • Deployment updates: updates on current deployments from manufacturers to Compass hosting locations.

Helpful Links:

  • Your Compass Dashboard for your order information.
  • Compass Status page for real-time updates on facility status.
  • Naming conventions for each facility here.

Facility Updates

Ohio 2: Our newest facility, Ohio 2 saw containers deployed last week. Units are now being configured for electrical work.

Minnesota 1: One container of units is offline after a part failed. We are working with the manufacturer to have the part replaced as soon as possible. As of now, we estimate the container will be offline until the first week of May.

Site expansion continues at Minnesota 1, with containers deployed but awaiting electrical parts from the manufacturer.

Texas 3: Most containers were offline over the weekend due to electrical work, but most are now back online. A few containers are still being brought back up, likely in the next 48 hours.

Texas 4: We have begun removing all Antminer S19 XP and S19a units from the site for redeployment to other facilities. Please refer to the email communication from our Chief Mining Officer for further information on these redeployments.

We will be hosting a client Q&A on Texas 4, which you can sign up for here.

All other unit types will remain at Texas 4.

Manitoba 1: The majority of units are now back online at various Manitoba locations. A remaining percentage of units are expected to come online this week or next in various locations in Manitoba. Please allow time for your dashboard to update to its new location.

South Carolina 2: Units are now offline and are prepping for servicing and shipment. We remain on schedule for redeployment in late April to early May.

Deployment Updates

Deployment note: Multiple bundles are now in the final stages of deployment across various facilities, including new facilities and facility expansions which were brought online to expedite delayed orders.

We are working on a final deployment package for delayed units to these facilities.

Mini Bundle 1: Over 100 units in Unit 6 were deployed last week. Unit 6 deployment is now 79% complete and will continue as containers are energized in Texas 3.

Mini Bundle 2: 48 machines deployed last week, with bundle 98% deployed.

LoneStar 1: Bundle is fully deployed. Please file a support ticket if your unit(s) is not online.

LoneStar 2: Unit 5 is fully deployed. Unit 6 is 27% deployed, awaiting final energization.

US-VIP: Units 10 is 96% deployed, with units 11-12 awaiting final energization.

RU-VIP: Bundle is 72% deployed, awaiting energization of units 10-12.

Next Generation Bundle and/or S19 XP Single Orders: Units are in queue for deployment in Texas 3. Please file a support request if you’d like to go online earlier at Ontario 1 or a Manitoba site with your Next Generation Bundle and/or S19 XP Single Order at a hosting rate of $0.079.

Unit allocations may go to alternative sites, depending on the best timeline for units to be energized.

KA3: All units, minus one set, have been fully deployed. Please file a ticket if your unit is not online.

L7: All units have been delivered and deployed.

Texas 4 S19j Pro 100: September batch is 42% deployed, with remaining units awaiting further energization.

Ontario S19j Pro 100: Customers were assigned temps, worker names starting with “ttx”. These units will hash to customers until their permanent unit is available. Email communications will be received for both the temp assignment and the permanent unit assignment.